[edit] Final Report (11 weeks effort, during months 1-16)
| Workpackage effort | lead | Oxford | Cam | OU | Starts | Ends |
| Total = 11 weeks | 5 | 3 | 3 | Nov 2008 | Feb 2010 |
Comments: edit comments
Deliverable:
- Final report on the support structures needed and the strategic decisions required to make use of a key emerging technology at an enterprise-level.
Comments: The skeleton of the draft final report, which is a summary of previous work and compilation of sub-reports, will be started in November for review in December. The final report will need be finished by end of January. End of project is end of March 2010/early April.
warning.png"{{{WP_Lead}}}" cannot be used as a page name in this wiki.